The Transmission Firm of Nigeria has introduced that there can be electrical energy outages in elements of Enugu State and Abuja, respectively, as a result of upkeep of its Kubwa and New Haven Enugu 132/33 kilovolt substations.
The spokesperson of TCN disclosed this in a separate assertion launched on the company’s X account on Tuesday.
In keeping with TCN, the scheduled Enugu-New Haven upkeep would take impact from October 22, 2025, to Thursday, October 31, 2025, between 9:00am and 5:00pm each day.
Consequently, TCN acknowledged that there can be disruption of bulk electrical energy provide to 1 33-kilovolt feeder per day on a rotational foundation in the course of the interval.
“TCN needs to make clear that this isn’t a complete system shutdown for Enugu State. To minimise disruption, the work has been rigorously deliberate to have an effect on just one 33 kV feeder per day on a rotational foundation. Provided that Enugu State is equipped by twenty-four (24) 33 kV feeders, this association ensures that almost all elements of the state will proceed to obtain an influence provide whereas the upkeep is ongoing.
“The train requires the non permanent isolation of particular 33 kV feeders to make sure the protection of TCN technical crews and the safety of apparatus beneath upkeep.
“Consequently, clients in areas served by these feeders will expertise energy interruption solely on the day their particular feeder is remoted,” the assertion reads.
In Abuja, the disruption, which is predicted to take impact on twenty first October 2025, would have an effect on areas in Kubwa, together with Military Resettlement, Papal Floor, Aso Backyard, Nydren Grocery store, Again of AT4, Again of Mobil, Zenith Financial institution, FO1, Kubwa Extension, Chikakore Group, Dantata Property, IITA Farms, Royal Champion Church, the Kubwa space and environs.
“The Transmission Firm of Nigeria (TCN) notifies the general public of scheduled preventive upkeep on the Kubwa 132/33 kV Transmission Substation on October 21, 2025, from 11 am to three pm.
“The train will contain the alternative of a 33 kV circuit breaker with a brand new one and would require an interruption of bulk energy provide to the Abuja Electrical energy Distribution Firm (AEDC) from Kubwa Substation,” the assertion reads.